Transmission Network Investment as an Anticipation Problem
Loading...
License
Cadmus Permanent Link
Full-text via DOI
ISBN
ISSN
1028-3625
Issue Date
Type of Publication
LC Subject Heading
Other Topic(s)
EUI Research Cluster(s)
Initial version
Published version
Succeeding version
Preceding version
Published version part
Earlier different version
Initial format
Citation
EUI RSCAS; 2010/04; Loyola de Palacio Programme on Energy Policy; [Florence School of Regulation]; [Energy]
Cite
RIOUS, Vincent, GLACHANT, Jean-Michel, DESSANTE, Philippe, Transmission Network Investment as an Anticipation Problem, EUI RSCAS, 2010/04, Loyola de Palacio Programme on Energy Policy, [Florence School of Regulation], [Energy] - https://hdl.handle.net/1814/13081
Abstract
This paper proposes a probabilistic model to evaluate if a proactive TSO that anticipates the
connection of new generators with short construction duration compared to the time needed to
reinforce the network is more efficient than a reactive TSO that does not make any anticipation but
that may then face higher congestion while the network is being reinforced. This evaluation is made in
presence of anticipation costs both related to the study of the project of network investment and to the
administrative procedures needed to obtain the building agreement. Our results in terms of social costs
clearly show a limit of probability for the connection of generators beyond which a proactive TSO is
more efficient than a reactive TSO. Evaluated on realistic cases of connection, this limit of probability
is found quite low, which indicates that the proactive behaviour for a TSO shall generally be the
optimal one.